These are the Queenstown Commissioners minutes for August 24, 2022. A 5:00 PM work session with Town Engineer Bob Rauch reviewed a phased water service analysis and options for the Wheatlands development, including increasing appropriation permits for the Town's wells, connecting Wheatlands via the Outlet Center water/sewer infrastructure, and the Town assuming ownership/establishing easements for private Outlet Center lines; Rauch stated there is sufficient treatment-plant capacity and infrastructure to support Phase 1 and will submit an official recommendation. In the regular meeting staff reported parts ordered for the treatment-plant compactor, a water main leak on First Ave that was repaired, and that Susquehanna will begin providing monthly operations reports; the Planning Commission’s proposed barbershop zoning definition was tabled for further review and the August 9, 2022 minutes were approved. Town finances were listed (General Fund $152.980.29 / Water-Sewer Fund 5126.575.95 / APRA Fund $657,811.51), Manager Moore reported meeting with property owner Peter Dudley about development and sewer/water capacity options, and she will gather ideas for a T‑Mobile Hometown Grants application; Activities Committee is recruiting members and planning events. A pre-bid meeting for marine/dock work had no-shows but some requests for bid documents and bids were due that day; there was no new business, no attorney updates, no public comment, and the meeting adjourned at 6:35 PM (votes noted 3 aye - 0 nay).
Show the raw extracted text
Exactly as extracted, unformatted — for checking against the original. The readable version is easier to read.
QUEENSTOWN COMMISSIONERS
August 24,2022
PRESENT: President Al Hardee, Commissioner Tom Willis, Commissioner Bryon Callahan,
Town Manager Amy Moore, Town Clerk Aaron Homey
WORI( SESSION CALLED TO ORDER AT 5:00 PM
Town Engineer Bob Rauch and James Cook were present to discuss phased water service
analysis findings and recommendations for development projects including Wheatlands. Topic
discussed were possibility of increasing the appropriations permits for the Town's two existing
wells, possibility of connecting service to Wheatlands via the Outlet Center w/s infrastructure
and Town assuming ownership of some Outlet Center w/s infrastructure. Wheatlands connecting
to County w/s system? Option for an in-ground tank systern on Town land or private in-ground
tank or tower on Wheatland property. After discussion, Rauch suggests Wheatlands be allowed
to connect via Outlet Center infrastructure and Town assume ownership of current private Outlet
Center lines/establish easements. States there is sufficient capacity at the treatment plant and
adequate infrastructure to support Phase 1 of the Wheatlands project. Rauch will submit an
official recommendation to the Town on how best to proceed.
Hardee motion to close the work session at 6:00pm. Willis second. VOTE: 3 aye - 0 nay.
REGULAR MEETING CALLED TO ORDER AT 6:00 PM
GUESTS
(None present)
PUBLIC WORIG
o
Parts for compactor at Treatment Plant have been ordered.
o
Water main leak on First Ave this morning, has since been repaired.
o if
R&M schedule for Plant was developed by Susquehannain2l2l, there was a question of
one was in place at last meeting. Will start providing monthly operations report to
Commissioners to review as provided by Susquehanna.
PLAI{NING COMMISSION
o
Zoning Ordinance amendment - Barbershop definition for review., Commissioners will
table until next meeting so they may review.
FINANCE COMMITTEE
(no updates)
HARBORMASTER
(no updates)
ACTIVITIES COMMITTEE
o Ms. Moore/Pres. Hardee met with 2 of current members to discuss roles and
procedures/responsibilities of committee. Will try to find more members to volunteer for
committee as 3'd member currently not able to fully commit to expected schedule/demands
of committee. Members currently discussing ideas for future events in town.
TOWN CLERI(
o
Treasurers/FinanceReport
General Fund $152.980.29 / Water-Sewer Fund 5126.575.95 / APRA Fund $657,811.51
.
Minutes
o
August 9,2022 (Regular meeting)
Willis motion to approve as written. Hardee second. VOTE: 3 aye - 0 na:t.
o
Correspondence/Requests/Info - Sent and Received
o
Metro Recreation rep informed that playground updates/repairs now expected to
begin around Decernber 2022. Delays due to supply chain issues.
TOWI\ MANAGER UPDATES
o
Met with Bob Rauch and Peter Dudley this aftemoon. Peter is getting some interest in his
property for residential development and wanted to know where we stood with capacity for
water and sewer. Bob reviewed the tower and flow issues we've had, as well as cunent
sewer plant capacity. Options to Dudley for sewer include expanding existing WWTP or
build own and town take over. Options for discharge would be to increase town discharge
permit and discharge dtown or do spray irrigation. He was informed of current water
tower status'and plans to put out to bid for more accurate pricing. He has no idea what
capacity will be required at this point. Is using the ternplate of the Town's Comprehensive
Plan. Will go back and bring in consultant/developer.
o
ESAM Fall dinner- Salisbury September 2l't - RSVP by 9ll5
o
T-Mobile Hometown Grants - $25 million, 5-year initiative to support organizations who
help small towns thrive and grow. Grants up to $50,000 given every quarter to up to 25
small towns. Community projects could be revitalizing a town hall, senior center, ball
field, etc. Thoughts on what we could apply for? Permanent Stage, electric,
pavilion/gazebo at park; ramp area: gazebo - maybe small pier?, boardwalk connector
project from ramp to Second Ave dock? Deadline to apply for this quarter is October I't.
Ms. Moore will gather a few ideas for potential projects to apply for.
OLD BUSINESS (no updatesfor Old Business ltems except as noted below)
INFRASTRUCTURE
I&IProject
1.
2. New Water Tower & Infrastructure Project
3. Wall St. Water Tower Maintenance
4. Otd Wharf Lane -Stormwater
5. Wall St. Water Line Replacement
MARINE PROJECTS
L. Boat Ramp Improvements
2. Town Dock Projects
Construction/Dredging Updates
^.
Pre-bid meeting held by Rauch last week- had no shows. Had a few companies
request bid docs. Bids due by today- will contact Rauch for update on any bids
received.
3. Federal Channel Dredging
POLICY
L. Review and Updates to Town Codes and Ordinances Q022)
2. Water/Sewer Connections Code - Proposed Clarifications & Revisions
3. Breezeline (Atlantic Broadband) RenewaVOptions
4. Codify Ordinances Adopted Since Last Update
DEVELOPMENT PROJECTS
1. Wheatland's Project
OTHER
L. Speeding on Main St
2. American Rescue Plan Act
NEW BUSINESS
(no updates)
ATTORNEY UPDATES
(no updates)
PUBLIC COMMENT
(no updates)
There being no further business, Hardee motion to adjourn the meeting at 6:35pm. Willis second.