Town Commissioners Minutes — 2022-04-07

Minutes April 7, 2022 · 1 page(s)

Read as text View original PDF ↗ Meeting

This emergency special meeting (April 7, 2022) addressed immediate failures at the Queenstown wastewater treatment plant: membrane train #2 is offline and train #1 was found damaged beyond repair, forcing the plant onto bypass and requiring both membrane replacements. Commissioners voted 2-0 to bypass normal procurement and use Town ARPA funds to purchase replacement Microdyn membranes from MMBR Systems at a quoted $83,980, and directed staff to contact other municipalities about similar failures and study alternative membrane types and any plant retrofit needs with Engineer Bob Rauch and Consultant George Frigon.

AI-generated summary — verify against the source document.
Show the raw extracted text

Exactly as extracted, unformatted — for checking against the original. The readable version is easier to read.

QUEENSTOWN COMMISSIONERS
EMERGENCY SPECIAL MEETING
April 7,2022
PRESENT: President Alton Hardee, Commissioner Bryon Callahan, Town Clerk Aaron Horney, Town
Attorney Lyndsey Ryan
The purpose of the emergency meeting was to discuss the operation of the wastewater treatment plant and
replacement of the treatment plant membranes.
MEETING CALLED TO ORDER AT 1:02 PM
Attorney Ryan gave a brief overview of the current conditions at the plant as follows:
o
Membrane train #2 is now offline as membrane damage discovered during recent cleanings has
now caused them to fail.
a Similar conditions were obseryed in Membrane train #1 during a subsequent cleaning.
a Train #1 is deemed to be damaged beyond repair and could fail at any time.
a The plant is cunently on bypass mode- both membranes must be replaced immediately.
a Town Engineer Bob Rauch and Town Plant Consultant George Frigon agree this is an emergency
situation and immediate action is required.
Current membranes in place are Microdyn brand- plant has been fit for this type of membrane-
plant would have to be retrofitted to accommodate different membranes.
a No time to bid out for replacements or find other options due to emergency situation.
a ARPA funds previously allocated to Town may be used to purchase new membranes.
a Current quote from MMBR Systems to supply/ship new membranes is $83,980- Town is looking
into if can be shipped faster than stated on quote as needed ASAP- may cause price quoted to
increase if so.
Hardee motion to bypass normal procurement process as immediate action required to p!'event damage
to the Town wastewater treatment plant and appropriate Town ARPA funds to purchase replacement
membranesfor the plant as quotedfrom MMBR Sltstems. Callahan second. VOTE: 2 ave - 0 naJt.
Pres. Hardee stated he had done research regarding similar membrane failures in Marathon, FL and would
like Ms. Ryan to contact local government officials there to obtain more information regarding their and
other municipalities issues with membranes. Comm. Callahan stated the Town should begin the process
of determining what other membrane types might be better to use in the future to replace the cunent type
used and what modifications would be needed at the plant to implement them. Should discuss with Bob
Rauch/George Frigon.
There being no further business, Callahan motion to adjourn the meeting at l:21 pm. Hardee second.
VOTE:2 ave-0nav.
WW
Town Clerk-T
An unhandled error has occurred. Reload 🗙

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.